Skip to content

INDUSTRIAL AIR CONDITIONING AND REFRIGERATION / DESIGN, INSTALLATION, SERVICE

Process temperature.
Production at ease.

Chilled water systems at 7/12 °C, chillers up to several hundred kW, free cooling, hall cooling and precision air conditioning. We start sizing from the heat balance and the load profile, not from the sum of nameplate ratings.

Send an installation enquiry
Chilled water parameters
7/12 °C; for machinery 12/18 °C
Design temperature difference
ΔT 5 K
Compressor efficiency
+2–3% per 1 °C of evaporating temperature
Precision air conditioning
±1 °C, ±5% RH
Free cooling
compressors off below +2…+5 °C
Chilled water buffer
3–5 l per 1 kW
An air handling unit on slings being lowered onto the roof structure by the installation crew
CLIMA LINE / INSTALLING AIR HANDLING UNITS AND CHILLERS, FOOD PLANTSee the project

PARAMETERS FOLLOW FROM THE TECHNOLOGY

No two halls
are the same.

Chilled water for machines, cooling of work zones or ±1 °C precision air conditioning for a process: selection starts with what happens in the plant, that is machine power, shift pattern, hall height and the stability the process needs.

FROM HEAT BALANCE TO COMMISSIONING

First we calculate.
Then we select.

Unit capacity is only part of the answer. What counts is the whole system: temperature and flow at the consumer under variable load, seasonal efficiency (ESEER/SEPR), the refrigerant and its GWP, service access and the cost of energy over 15–20 years of operation.

  1. 01

    Heat balance and thermal audit

    Machines, building, air exchange, production rhythm; measurements at peak periods instead of a per m² rule of thumb.

  2. 02

    A system matched to the process

    Water parameters, consumers, control strategy, choice of refrigerant and a capacity reserve justified by the consequences of downtime.

  3. 03

    Designed for operation from day one

    Service access, hydraulic balancing, heat recovery, free cooling and trend logging after commissioning.

REQUIREMENT → PARAMETER → DELIVERY → PROOF

Cooling
in numbers.

The most common requirements of manufacturing plants and how we prove they are met after commissioning.

Industrial refrigeration and air conditioning: requirements and proof
RequirementParameterHow we deliverHow we prove it
Process cooling for machineryChilled water 12/18 °C instead of 7/12 °C, ΔT 5 KIndirect system on water or glycol with a 3–5 l/kW bufferΔT measurement on the return, report with settings after commissioning
Capacity matched to the facilityLoad simultaneity factor 0.6–0.8; server room: +10–25% above IT loadThermal audit of gains from machinery, building envelope, lighting, people and ventilationHeat balance in the concept with an annual energy cost forecast
Stable parameters in a precision zone±1 °C and ±5% RH, SHR 0.9–1.0Precision air conditioning units, N+1 redundancy with unit rotationTemperature and humidity trend in the BMS
F-gas obligationsThresholds of 5, 50 and 500 t CO₂eLow-GWP refrigerant, indirect system with the charge contained in the plant roomLeak checks every 12/6/3 months, entries in the CRO
Energy cost all year roundFree cooling below +2…+5 °C outdoorsGlycol with a free cooling module, heat recovery from condensersSeveral hundred to several thousand hours of compressor-free operation per year

Where does an industrial refrigeration design start?

Industrial refrigeration is part of the production technology, not comfort air conditioning with more capacity. An injection moulding machine running too hot, a CNC laser without cooling or temperature swings in a semi-finished goods store mean downtime, a scrapped batch and losses in the hundreds of thousands of zlotys. The scope covers process cooling of machinery (injection moulding machines, lasers, presses, furnaces, glass tempering and fusing stations), cold and freezer rooms for the food industry, including solutions for frost build-up and air dehumidification, and heat recovery from condensers for hall heating and domestic hot water. That is why we start with a thermal audit: we sum the gains from machinery (in glass plants the tempering furnaces dominate the balance) plus solar gains, lighting, people and air exchange.

The balance gives the cooling capacity and the reserve for heatwaves. Undersizing ends with a lost parameter in July; oversizing ends with a chiller cycling at low load, more expensive to buy and quicker to wear out its compressors. The sum of machine nameplate ratings is not the chiller capacity: the real simultaneity factor lies in the range 0.6–0.8. The order is fixed: first we limit heat gain at the source (machine enclosures, local extraction, recovery), then we select the cooling capacity.

How do you select the chilled water parameters, buffer and free cooling?

The classic chilled water parameter is 7/12 °C for air-side consumers; when cooling machinery only, 12/18 °C is sufficient. Raising the evaporating temperature by each 1 °C improves compressor efficiency by about 2–3%, so the parameter affects the annual energy cost more than the chiller brand. Water returns to the chiller warmer by the design difference, most often 5 K.

We size the chilled water buffer at 3–5 litres per 1 kW of cooling capacity, and even more for consumers with step loads; too small a system volume means compressor cycling and parameter swings at the machine. A glycol system with a free cooling module switches the compressors off completely below +2…+5 °C outdoor temperature. With three-shift operation that is several hundred to several thousand hours a year in which cooling costs only the energy for pumps and fans.

Air-cooled or water-cooled chiller, DX or indirect system?

A chiller with an air-cooled condenser is the default solution for most plants in Poland: it needs no cooling tower, no water treatment and no Legionella risk management, and with free cooling the difference in annual efficiency largely disappears. A water-cooled condenser makes sense above several hundred kW with continuous operation and limited space outside the building. In a typical process installation the chiller accounts for roughly half of the total cost.

The choice between direct expansion (DX) and an indirect system determines operating costs for 15–20 years. DX is more efficient and cheaper to install with one or two consumers close to the chiller, but it has a large refrigerant charge throughout the installation, and leaks are harder to locate. An indirect system contains the refrigerant in the plant room, with a charge several times smaller, which simplifies F-gas obligations and service, at the cost of a 2–4 K loss across the heat exchanger. It is the standard with many consumers spread across the hall; in a production plant it almost always wins, because one failure does not stop the whole production, and adding another consumer does not require intervention in the refrigerant circuit.

Which refrigerant should you choose as F-gases are phased out?

The leak check thresholds of 5, 50 and 500 t CO₂e are set by the CO₂ equivalent (charge mass × refrigerant GWP), not by the refrigerant mass alone. Synthetic refrigerants are the simplest to service, but R410A has a GWP of 2088, R134a 1430, while newer HFOs go below 10. The F-gas Regulation limits the quota of synthetic refrigerants on the EU market, which raises the price of refrigerant when installations are topped up.

Ammonia R717 (GWP 0) gives the highest efficiency at large capacities, is cheap and is not subject to F-gas limits, but its toxicity and flammability require a separate plant room, detection, emergency ventilation and trained operators, so it is justified only above several hundred kW. Carbon dioxide R744 (GWP 1) is safe and unrestricted, but it operates at 80–120 bar, which raises installation cost and requires different service competences; it performs best in freezing applications. For a typical plant with process cooling in the range from several tens to several hundred kW, the calculation points to an indirect system on a low-GWP refrigerant, below the 500 t CO₂e threshold: one check a year instead of four. We deliver projects throughout Poland, with a concentration in Silesia.

How does precision air conditioning differ from comfort cooling, and how do you cool a production hall?

Precision air conditioning for server rooms and technical rooms, measurement laboratories, stores for sensitive substances, cleanroom support areas and metrology zones holds ±1 °C and ±5% RH; a comfort system works with a tolerance of ±2–3 °C and usually does not control humidity. Precision units have a sensible heat ratio (SHR) of 0.9–1.0 compared with 0.65–0.75 for comfort units, so almost all their capacity goes into cooling, not dehumidification. A comfort split gives 25–35% of its capacity to dehumidification and is not designed for 24/7 operation at low winter temperatures.

A split is sized on room volume and solar gains, while in a production hall the dominant heat gain comes from machinery. A production hall needs zonal cooling, not volume-based cooling: in a building a dozen or more metres high you cool the working zone, not the space under the roof. We use local cooling of workstations, air curtains and supply air with destratification, and with gains of several hundred kW, a chilled water system with fan coil units or AHUs with cooling coils. From 11 January 2027 the temperature in a hall may not exceed 35 °C, and the obligation to act arises once 28 °C is exceeded.

Condensing unit with compressor and control cabinet on a roof during installation

AFTER HANDOVER, WE STAY ON

The installation runs.
We keep watch.

Inspections twice a year, leak checks every 12/6/3 months depending on the CO₂e charge, a report with setpoints after every visit. Response time from 3 h, with the threshold set in the SLA contract separately for each system. Without inspections an installation loses efficiency unnoticed: a fouled condenser or a refrigerant loss raises energy consumption long before it causes a breakdown.

See Clima Line service

GOOD QUESTIONS TO START WITH

Before we select
a solution.

LET’S START WITH YOUR PROCESS

Your technology.
Our engineering.

Describe what your production needs: facility, parameters, deadline.
An engineer replies, not a sales team.

Send an enquiry